2015-09-18

Man cave: Day 14

Electrical work done. I have lights. I even have a loft light. Electrical work by LA Electrical, and Lee seems to do a good job.

Some more paint on the walls now, but more to be done next week. Ceiling was not dry enough for paint today.

Apart from the outside door and window when they arrive, it is all internal, worktops, shelves, decorating now.

I do have one door, the internal door, with the lock all connected and tested. It needs some final fixing to do on Monday, but apart from that Monday is decorator. The rest of the week is decorator and carpenter. Loft hatch is here and will be installed once ceiling is painted.

Oh, and Sandra got me a sign :-)


1 comment:

Comments are moderated purely to filter out obvious spam, but it means they may not show immediately.

Deliveries from China

I have PCBs made in China (well Hong Kong). This is all my many small PCB projects (not FireBrick). I would rather use UK suppliers but I am...